Stage 1: Widen south side of Tualatin-Sherwood Road from Olds Place to 124th Avenue
Widen north side of Tualatin-Sherwood Road from 124th Avenue to Teton Avenue
Stage 2: Widen south side of Tualatin-Sherwood Road from 124th Avenue to 120th Avenue
Stage 3: WWSP pipeline installation
Stage 4: Widen north side of Tualatin-Sherwood Road from Olds Place to 124th Avenue
Widen soouth side of Tualatin-Sherwood Road from 124th Avenue to Teton Avenue
Stage 5: Construction of medians and islands
Stage 6: Final paving and striping