Construction stages

Stage 1: Widen south side of Tualatin-Sherwood Road from Olds Place to 124th Avenue
               Widen north side of Tualatin-Sherwood Road from 124th Avenue to Teton Avenue

Stage 2: Widen south side of Tualatin-Sherwood Road from 124th Avenue to 120th Avenue

Stage 3: WWSP pipeline installation

Stage 4: Widen north side of Tualatin-Sherwood Road from Olds Place to 124th Avenue
               Widen soouth side of Tualatin-Sherwood Road from 124th Avenue to Teton Avenue

Stage 5: Construction of medians and islands

Stage 6: Final paving and striping

 